NORTHLIGHT POWER / TECHNICAL REVIEW
Natural hydrogen
at mine sites.
NorthLight Power proposes a $250,000 evaluation with a mine operator to test whether natural hydrogen at one property could displace diesel used for electricity.
WHY START AT MINE SITES?
Existing knowledge.
A local energy need.
Mine properties bring geological records, drill core, boreholes and operating infrastructure into the same setting as an established energy customer. Together, these can provide a focused starting point for natural hydrogen evaluation.
Researchers measured hydrogen in gas from five Thompson boreholes and monitored gas discharge over several years at Kidd Creek. At Goose and Mary River, iron-bearing rocks warrant investigation. We found no verified site-specific hydrogen concentration for either mine in the records reviewed.
01 / THE MINING PRESENTATION
Natural hydrogen development
at operating mines.
The nine priority sites and eight additional assessed properties are mapped separately. Each slide includes its technical basis and source references.
Open the presentation ↗Download HTML presentation ↓
EVALUATION SEQUENCE
From drill core to mine power.
-
01 Property review
Select sampling intervals
Use drill core, borehole logs and records of water inflow to identify fractures for sampling. Confirm which intervals the mine can access.
View the field plan Slide 10 -
02 Field measurements
Test for sustained flow
Measure hydrogen concentration and gas and water flow at an isolated fracture. Track discharge and pressure recovery over time.
View the sampling protocol Slide 11 -
03 Development assessment
Match supply to demand
If flow persists, estimate net electricity after recovery and conversion losses. Compare that output with the mine’s load profile to identify when backup power would be needed.
View the engineering assessment Slide 14
02 / FUEL RECORDS FOR THE NINE PRIORITY SITES
Mine fuel records.
Reporting boundaries.
For each of the nine priority sites, the register identifies diesel use and its reporting period alongside the geological evidence for hydrogen. Expand a row for the source and the scope of the measurement.
Diesel figures cover different years and uses, from power generation to the entire operation. Amaruq is already included in Meadowbank. Adding the rows would double-count fuel and mix operating records with forecasts.
| Order | Property / region | Screening score | Annual diesel use & basis | Hydrogen evidence | Details |
|---|
How the estimates were prepared
Meadowbank and Meliadine use 2025 operator-reported diesel energy divided by 0.03868 GJ/L. This is a standardized volume equivalent, not directly reported litres. Other figures retain their source’s scope and period.
NRCan energy conversion basis ↗Before selecting a first partner
Confirm current fuel ledgers, electricity-generation fuel, mine-life assumptions and access. The geological scores describe the information available for investigation. Screen the energy application against the site’s eligible electrical demand and its operating hours.
03 / AN ILLUSTRATIVE ENERGY SCENARIO
From hydrogen
to net electricity.
Explore the assumptions. This is an educational calculation, not a resource estimate, project forecast or equipment specification.
INDICATIVE ANNUAL OUTPUT
Supply-side equivalent only, before any cap for eligible site demand. Gross avoided fuel value excludes project capital, operating costs and financing; it is not profit or NorthLight revenue.
Calculation and assumptions
Electricity (kWh/year) = H₂ discharge (t/year) × recovery fraction × 33,000 kWh/t × net electrical efficiency. Diesel equivalent (L/year) = electricity ÷ existing generator kWh/L. Gross avoided fuel value = equivalent litres × delivered cost per litre. The 33,000 kWh/t basis follows the corrected PNAS unit. All adjustable inputs are illustrative; actual performance, recoverability, costs and demand need site-specific evidence.
Published unit correction ↗04 / SOURCES & REVIEW STATUS
Sources and measurement basis.
Property assessment
Denis Brière, 17 Mine Properties of Merit Report, November 2026. Screening scores and ranks appear on p. 1. Pages 3–19 review the individual properties. The site numbers follow the property list on p. 2.
Scientific evidence
Sherwood Lollar & Warr, PNAS, May 2026. Read with the June unit correction. Figure 5 reports the Kidd Creek borehole time series. The authors extrapolate mine-wide discharge. Converting chemical energy into electricity requires an efficiency assumption.
Kidd Creek paper ↗ Correction ↗ Thompson measurements ↗NorthLight approach
Current website presentation; Mine-Site Hydrogen Evaluation Agreement Framework, 14 October 2026; Torys draft dated 10 November; technical comments and regional evidence circulated 13–17 November.
NorthLight presentation ↗ Draft agreement summary ↗Fuel research
Operator sustainability data, regulatory annual reports and technical design studies. Source links and table/page references are included within each property row and in the CSV. Fuel and hydrogen records reviewed 19 November 2026.
Technical review items before external presentation
- Confirm operator participation, interval access and the energy application before fieldwork.
- Reconcile the framework, measurement plan and legal draft with Barbara’s November guidance. The proposed field scope requires operator authorization.
- Confirm current mine status, fuel reporting boundaries, access and eligible loads directly with each operator.
- Replace historic fuel baselines and design proxies with operator-approved current values before using them in a commercial offer.